Adobe - Big Savings Alert – Don’t Miss This Deal - Ends In 1d 00h 00m 00s Coupon code: 26Y30OFF
  1. Home
  2. Adobe
  3. AD0-E903 Exam
  4. Free AD0-E903 Questions

Free Practice Questions for Adobe AD0-E903 Exam

Pass4Future also provide interactive practice exam software for preparing Adobe Workfront Project Manager Professional (AD0-E903) Exam effectively. You are welcome to explore sample free Adobe AD0-E903 Exam questions below and also try Adobe AD0-E903 Exam practice test software.

Page:    1 / 14   
Total 70 questions

Question 1

The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?



Answer : B

For the art director to only receive email notifications about new proofs or versions, the option 'Disabled and Notify recipients about this proof is selected' is the correct choice. This ensures that they are not inundated with notifications about every comment or decision made but are alerted when a new proof or version is uploaded for review.

This approach optimizes the notification settings based on the user's request, providing a more focused and less overwhelming email experience, which is often crucial for roles such as creative directors who manage multiple proofs and versions.


Question 2

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?



Answer : B

In Adobe Workfront, Condition is the reportable variable that is determined by the relationship between the Planned, Projected, and Estimated Dates. The Condition field reflects whether a project is On Target, At Risk, or In Trouble based on how its actual progress aligns with the planned schedule and dates. It allows project managers and stakeholders to quickly assess the health of the project.


Question 3

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?



Answer : B

In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of 'Must Start On.' This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.


Question 4

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?



Answer : A

The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.


Question 5

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?



Answer : C

The best practice is to incorporate an approval process into the project template so that it is automatically triggered when a project reaches the completion stage. This ensures consistency and saves time by removing the need to manually set up approval processes for each new project. This approach also guarantees that the Project Sponsor's review is systematically included before the project is officially closed.


Page:    1 / 14   
Total 70 questions