Free BCS Foundation Certificate in IS Project Management (ISEB-PM1) Practice Questions

These BCS ISEB-PM1 sample questions are a small glimpse of our full set of BCS ISEB-PM1 actual questions. They give you a preview of what the real ISEB-PM1 exam might look like and the contents of Pass4Future's premium BCS ISEB-PM1 product. You must not underestimate the value of BCS ISEB-PM1 practice exam questions, as they allow you to understand the actual BCS Foundation Certificate in IS Project Management exam in greater depth. Using them will save your time and money otherwise wasted in BCS Foundation Certificate in IS Project Management exam reattempts. Study guides and tutorials provide you with theoretical details about the ISEB-PM1 exam; these ISEB-PM1 practice exam questions prepare you to pass the exam. Get Pass4Future's premium access to continue your ISEB-PM1 exam practice with the complete set of BCS ISEB-PM1 realistic questions. Our BCS ISEB-PM1 practice questions come in various formats; make sure to check out the details and free demo of each format.

BCS ISEB-PM1 Sample Exam Questions

Page:    1 / 14   
Total 625 questions

Question 1

What is Project Portfolio Management?



Answer : D


Question 2

Which of the following is TRUE about most project life cycles?



Answer : B


Question 3

Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?



Answer : B


Question 4

Information collected on the status of project activities being performed to accomplish the project work is known as what?



Answer : B

Work Performance Information

Part of the executed project management plan includes the routine collection of work performance information. The information gathered is important, and is useful as input data for quality control measures and programs. It is also useful when audits, quality reviews, and process analyses are conducted. This is especially true of work performance information collected which includes technical performance measures, project deliverables status, required corrective actions, and performance reports. Pertinent work performance Information is essential to the project management plan and includes, but is not limited to:

* Status information on schedule progress.

* Whether deliverables have been completed, or not.

* Start and finish status of schedule activities.

* Quality standards expectation results.

* Authorized costs vs. costs incurred to date.

* Estimated completion time for scheduled activities in progress.

* Percentage of physical completion of in-progress schedule activities.

* Experience based knowledge acquired, documented, and posted to knowledge base.

* Details of resource utilization.

Gathering and analysis of work performance information is essential to the project management plan and should be considered a priority. Work performance information contributes to the efficient use of resources, identifies potential trouble spots and problems, and serves as an effective project management tool. This term is defined in the 3rd and the 4th edition of the PMBOK.


Question 5

Which is a tool used in monitoring and controlling project work?



Answer : B


Page:    1 / 14   
Total 625 questions