These CIPS L3M3 sample questions are a small glimpse of our full set of CIPS L3M3 actual questions. They give you a preview of what the real L3M3 exam might look like and the contents of Pass4Future's premium CIPS L3M3 product. You must not underestimate the value of CIPS L3M3 practice exam questions, as they allow you to understand the actual Contract Administration exam in greater depth. Using them will save your time and money otherwise wasted in Contract Administration exam reattempts. Study guides and tutorials provide you with theoretical details about the L3M3 exam; these L3M3 practice exam questions prepare you to pass the exam. Get Pass4Future's premium access to continue your L3M3 exam practice with the complete set of CIPS L3M3 realistic questions. Our CIPS L3M3 practice questions come in various formats; make sure to check out the details and free demo of each format.
Do you know that you can access more real CIPS L3M3 exam questions via Premium Access? ()
Which of the following is least likely to be called a 'spot' purchase?
Answer : B
The three-year contract is a term contract.
The other requirements shown are of a 'one-off' nature, and could therefore be called 'spot' purchases.
Where the supplier guarantees to make good any losses suffered by the buyer as a result of product defects, for example
Answer : C
Indemnity.
As in 'an indemnity clause'.
'The supplier hereby indemnifies the buyer against / in the event of...'
Which two of the following constitute part of a common risk assessment or risk evaluation formula?
Answer : B, C
What is the likelihood of an event occurring?
What will be the impact of that event occurring?
This is the basis of almost all modern risk management.
CIPS has good content at Advanced Diploma level on the subject of Risk Management, and I have prepared tests for the two subjects in this area. :)
Sadgrove's book on business risk, in my view, is excellent; and NN Taleb's work (eg 'Antifragile') on risk, although difficult is, in my opinion, fascinating.
'When the best XXX is selected, a formal YYY ZZZ is prepared and sent to the supplier. Choose the most likely words to replace XXX, YYY and ZZZ.
Answer : C
The best quotation is selected, which would meet the specification as well as meeting the other re-quired criteria; and in order to progress things round the procurement cycle, a purchase order would be issued.
'Because they are set up for a specified duration, XXX contracts are subject to expiry rather than completion, unless they are renewed or extended.'
Answer : B
Term contracts are set up for a period of time, or a 'term'.
The other answer options shown here are the subject of other QUESTION NO : s within this test.