Pass4Future also provide interactive practice exam software for preparing SAP Certified Application Associate - SAP S/4HANA Cloud, public edition - Asset Management (C_S4CAM_2308) Exam effectively. You are welcome to explore sample free SAP C_S4CAM_2308 Exam questions below and also try SAP C_S4CAM_2308 Exam practice test software.
Do you know that you can access more real SAP C_S4CAM_2308 exam questions via Premium Access? ()
What are key activities of the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
Answer : A, C, E
The key activities of the Prepare phase of the SAP Activate methodology are project setup, starter system provisioning, and customer self-enablement. User training and data migration are part of the Realize phase.
Which process steps are available with the Overhead Maintenance (4WM) process? Note: There are 3 correct answers to this question.
Answer : A, B, C
The process steps available with the Overhead Maintenance (4WM) process are maintenance backlog overview, assign a general task list to the maintenance order, and review and release maintenance orders. Release the supplier invoice is part of the External Maintenance (4WE) process. Create maintenance plans for maintenance items is part of the Preventive Maintenance (4WP) process.
What can you use the View Browser app to do?
Answer : C
The View Browser app can be used to get a list of all available analytical CDS views and their artifacts. The other options are not possible with this app.
What are your options if an out-of-the-box integration between SAP S/4HANA Cloud and another SAP solution is NOT available?
Note: There are 2 correct answers to this question.
Answer : C, D
If an out-of-the-box integration between SAP S/4HANA Cloud and another SAP solution is not available, you can use custom CDS views or integration tools to build your own integration. Unrestricted firewall and Infrastructure as a Service are not relevant for this scenario.
In which implementation phase do you perform data load preparation?
Answer : B
Data load preparation is performed in the Prepare phase of the implementation project. This includes defining the data migration strategy, identifying data sources, and preparing data templates.