Pass4Future also provide interactive practice exam software for preparing Scaled Agile SAFe for Teams SP (6.0) - SAFe Practitioner (SP-SAFe-Practitioner) Exam effectively. You are welcome to explore sample free Scaled Agile SP-SAFe-Practitioner Exam questions below and also try Scaled Agile SP-SAFe-Practitioner Exam practice test software.
Do you know that you can access more real Scaled Agile SP-SAFe-Practitioner exam questions via Premium Access? ()
What is one component of the Continuous Delivery Pipeline?
Answer : A
Continuous Exploration (CE) is one of the four aspects of the Continuous Delivery Pipeline (CDP), along with Continuous Integration (CI), Continuous Deployment (CD), and Release on Demand1.CE focuses on creating alignment on what needs to be built by applying design thinking and Lean startup principles2.CE involves generating and validating hypotheses, defining a Minimum Viable Product (MVP), and developing a vision, roadmap, and features for the solution2.CE enables the enterprise to understand the market problem or customer need and the solution required to meet that need2.Reference:Continuous Delivery Pipeline,Continuous Exploration
What is one of the Agile Release Train events?
Answer : C
A Solution Demo is one of the Agile Release Train events. A Solution Demo is a periodic event where the current state of the Solution is evaluated by the relevant stakeholders, including customers and users. The Solution Demo provides an opportunity to inspect and adapt the Solution, and to validate that it meets the Solution Intent and the customer needs. The Solution Demo is typically held at the end of each Program Increment (PI), and may also be held more frequently depending on the Solution context and feedback mechanisms.Reference:Solution Demo - Scaled Agile Framework,SAFe for Teams - Know Your Role on an Agile Team | Scaled Agile,Exam Study Guide: SP (6.0) - SAFe Practitioner - scaledagile.com
During the PI Planning event, when are planning adjustments agreed upon?
Answer : D
During the PI Planning event, planning adjustments are agreed upon during the management review and problem-solving meeting, which is the last activity of the first day of the event1.In this meeting, the management team reviews the draft plans of the teams, identifies and resolves any issues, risks, or dependencies, and makes any necessary changes to the scope, people, or resources1.The management team also communicates the planning adjustments back to the Agile Release Train (ART) the next day, before the teams continue their planning and make the appropriate adjustments2.Reference:PI Planning,Management Review and Problem-Solving
User business value and time criticality are components of what?
Answer : D
user business value and time criticality are components of Cost of Delay (CoD), which is a measure of the economic value of a job over time. CoD is used to prioritize jobs based on the Weighted Shortest Job First (WSJF) model, which is part of the SAFe methodology. CoD is calculated as the sum of three components: user/business value, time criticality, and risk reduction and/or opportunity enablement. User/business value indicates the relative importance and revenue impact of a job. Time criticality indicates the urgency and value decay of a job.Risk reduction and/or opportunity enablement indicates the long-term benefits of a job12.Reference:1:WSJF - Scaled Agile Framework2:WSJF = (Biz Value + Time Crit. + Risk Reduce) / Job Size
What is part of the role of Product Management?
Answer : A
One of the roles of Product Management is to assign business value to Features. Features are services provided by the system that fulfill stakeholder needs. They are the primary artifact for defining, managing, and prioritizing the work of the Agile Release Train (ART). Product Management is responsible for defining and prioritizing the features in the Program Backlog, as well as assigning a business value to each feature based on its expected benefits and costs. The business value is used to guide the economic decision-making and trade-offs during PI Planning and execution. Product Management also collaborates with other roles, such as Solution Management, System Architects, and Business Owners, to ensure that the features align with the solution vision and roadmap, and meet the quality standards and nonfunctional requirements.Reference:Features - Scaled Agile Framework,Product Management - Scaled Agile Framework